March 26
|
-
Help Desk calls the Department Head to invite this group to move to
Artemis.
|
|
March 28
|
|
|
April 2
|
-
Coordinator and Help Desk:
-
create final list of users
-
decide how to handle old generic accounts
-
select Migration Day when
-
most users will be available
- AT
can send a Migration Team to that department
-
List is sent to MINS
|
|
April 9
|
-
User accounts created on Artemis
|
|
April 13
|
-
Preliminary migration of data by MINS
-
Coordinator reminds everyone in department that Athena access will be
disconnected at 4 p.m. on the day preceding Migration.
|
April 16
4 p.m
|
-
Final migration of data. Access to Athena will be disconnected at
4 p.m.
|
|
April 17
|
-
AT Migration Team visits department to install new software and assist users in changing Novell
password.
-
Coordinator maintains list of "absent" users for follow-up visits by
AT.
|